NATIONAL PARK SERVICE

FORT SUMTER DOCK RENOCAVATION

Charleston, SC |  2020 - 2022

Our team worked to minimize the impact of those schedule changes. There were issues regarding COVID safety, material long lead times, and site conditions. In the first progress meeting SIRIS identified a design issue that was a significant risk to the park and would reduce the amount of available visiting hours by 50%. We worked with NPS, the ferry concessionaires and designers to develop a redesign solution that would utilize only the long lead materials purchased by the contractor to create a solution that would increase the height of the fendering system by 8 feet. Due to the supply chain challenges and redesign, this solution allowed us to save 6 months and save over $500,000.